I have a project sheet that has worked perfectly for about 10 months. It has lots of dependencies already set up.
I made a copy of the sheet and removed all of the dates (highlighted them all and deleted). I have changed the names of some of the rows but the duration of every task and it's depedecies are still there (which is what I want)
Now when I start putting dates into some of the lines, those rows that are dependant are not linking to the rows they depend on.
Hopefully you can make out the screenshot. Row 208 had a duration and is dependant on row 207 but it doesn't appear on the Gannt chart. The same for row 209.
Any thoughts