it´s possible to have a report shared to a anyone without share the main sheet (data source sheet)
Thanks,
Hi Guilherme,
Yes, as a published read-only version or thru cell linking and reporting on the linked information.
Would that work?
Have a fantastic day!
Best,
Andrée Starå
Workflow Consultant @ Get Done Consulting
Hi there,
Another option would be to use it as a Widget on a Dashboard, where it essentially does the same thing as publishing (in that you do not need to share the underlying sheets) but you do not need to publish the item. Here's some information on that.
I hope this helps!
Alison
Hi Andrée
Actually I would use the report sheet as "interface" for tasks updates directly into data source sheet. But I intended to make sure each users see only their tasks. I can do that using a report feature, but it wont work if I must share the data source sheet (they will have full access thru it)
@Guilherme Ribeiro did you ever figure out a solution to this? I am running into the same problem.
Hi everyone,
i am looking for the answer for the first question (quoted).
It is absolutely necessary to share report but keep the source data (in the sheet) secured and hiden. That should be the main goal of sharing reports.
Does final solution coming?
thank you very much in advance
My manager set up a weekly smartsheets attachment of a sheet to be emailed to them every week. She now wants to turn this off but when her and I go into the Send as Attachment section of the page it only shows that two were sent instead of weekly for the last year or two and there is no way to turn anything off. How do I…
I have a large master sheet that I do not want anyone to have access to except the small team of admins. Is there a way for everyone in a dept to see the projects their dept are involved in (this is defined by a column), but only the PM can make edits to it? Bonus points if we can sort by "Status" then by "Kick-Off Date".…
Is there a way to have a master report that is pulling in the data from all of the necessary sheets and then several minor reports off this one where certain rows can be shown in certain sheets? The reason for this is because as projects get created in the workspace the admin then has to go into 5 reports and link the new…