Sanity check needed
For the PM's out there
Duration: 1 hour
Pred: 23FS - 1h
Duration: 1 hour
Pred: 23FF
should both start and end at the same time (that is start 1 hour before 23 ends and finishes when 23 ends)
I'm not missing something there, am I?
While the first is allowed, perhaps it should not be as that invalidates the "predecessor must finish before I can start".
Craig
Comments
-
Hi Craig
I agree with what you say, I suspect the first is simply handled as an FF.
Andy
-
Craig, you are correct in that both tasks will start and finish at the same time, which is 1 hour before row 23 finishes.
This is just how lag days work, you can link a task to another with predecessors but can add positive or negative lag days to get the exact start/end times you are looking for.
Predecessors will link tasks together but are not constraints (which exist in MS Project). Because it is not a hard constraint, there is not "predecessor must finish before I can start" logic.
-
Thanks Travis.
By practice, I'm going to avoid #FS-lead in the future.
It confused me (as you said MS Project would not have let me do that) and might again.
Craig
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 63K Get Help
- 380 Global Discussions
- 212 Industry Talk
- 442 Announcements
- 4.6K Ideas & Feature Requests
- 140 Brandfolder
- 129 Just for fun
- 130 Community Job Board
- 449 Show & Tell
- 30 Member Spotlight
- 1 SmartStories
- 305 Events
- 34 Webinars
- 7.3K Forum Archives