I'm using 5 day work week but have some tasks identified in my schedule that may occur over a weekend based on previous dependencies. Example, we are placing concrete for pour 1 and it happens to land on a friday, we need three days to cure before stressing. With a 5 day work week selected in doesn't count the weekend as cure time, so we lose 2 days on the schedule because it starts cure time on Monday rather than Saturday. I'm using predecessors so that if the schedule changes everthing moves with it. If I enter a date with out the predecessor I will have to remember each item and manually make changes.
Is there a work around when I enter predecessors that tells the program to count the weekend even though I've selected a 5 day work week?