Setting start date for Calendar

Karen Nankervis
Karen Nankervis ✭✭
edited 12/09/19 in Archived 2015 Posts

Hi, I've just started using Smartsheet so hoping it will do all the things I need.

My chart calendar starts in September 2014 even though all the things on my chart are from March 2015, how do I fix this, I don't want to have to move the bar along every time

thanks Karen

Comments

  • JamesR
    JamesR ✭✭✭✭✭✭

    I believe you are are talking ablou the Gantt chart view? Β If so in the Gantt Chart Settings (cog symbole top bar left corner of Gantt Chart) there is an option to open to current date ubder Timeline Display..

  • Travis
    Travis Employee
    edited 06/01/15

    JamesR suggestion of setting the Gantt chart to open to todays date will fix this for you but it sounds like you may have a task that was scheduled for September 2014 (possibly by mistake). I would check the dates in your sheet or scroll through your Gantt chart and see if there are any Gantt bars that go back that to September 2014.

  • Claire Diener
    Claire Diener ✭✭

    Is there a way to not have the ganyy chat open to today's date, but open to 5 days before today's date? I want to easily see which items have not been completed by the they are assigned, and don't want to have to scroll on the gannt side of the sheet.

    Thanks!

  • BobbyLite
    BobbyLite ✭✭

    Claire, there isn't a way to open the Gantt chart to five days before todays date... Your best bet will be to open the sheet then scroll slightly to the left in the Gantt

  • JamesR
    JamesR ✭✭✭✭✭✭

    Claire,

    Β 

    This sound like a job for conditional formatting, involving a calculation based on the comparison of the end date and todays date and the % complete column. The result could be used to conditionaly format any tasks that have not been completed by thier due date or could use a symbol field to Flag them. Β You would then not need to sctroll the Gantt chart.

  • Claire Diener
    Claire Diener ✭✭

    Thanks, James. Yes, I already have some conditional formatting in use - changing the color of text, and flagging them, I was just hoping for one more visualy representative element with the gantt.

  • JamesR's suggestion worked for me!Β  Thanks!Β  I was so tired of scrolling right.Β  The setting wheel was a little hard to find but it is there if you scroll all the way to the left (start date) of the gantt.