Limitations of MS Project import into Smartsheets
hanst
✭✭
Hi all
what are the limitations of MS Project imports into smartsheets?
the following is imported
- task, start, end date
- predecessors
- completion %
know of the following is not imported:
- Base line
- Parent predecessors
what else is not imported?
Comments
-
Hi Hans,
This information might be helpful!
https://help.smartsheet.com/articles/504553-import-files-to-create-new-sheets
Have a fantastic weekend!
Best,
Andrée Starå
Workflow Consultant @ Get Done Consulting
SMARTSHEET EXPERT CONSULTANT & PARTNER
Andrée Starå | Workflow Consultant / CEO @ WORK BOLD
W: www.workbold.com | E:andree@workbold.com | P: +46 (0) - 72 - 510 99 35
Feel free to contact me for help with Smartsheet, integrations, general workflow advice, or anything else.
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 63.5K Get Help
- 402 Global Discussions
- 213 Industry Talk
- 450 Announcements
- 4.7K Ideas & Feature Requests
- 141 Brandfolder
- 135 Just for fun
- 56 Community Job Board
- 454 Show & Tell
- 31 Member Spotlight
- 1 SmartStories
- 296 Events
- 36 Webinars
- 7.3K Forum Archives