Are lag times calculated based on working days (i.e. weekdays)? Is there a way to setup a lag time for a finish-to-finish dependency based on elapsed dates/calendar days? For example, if I have a report date milestone of June 1, 2016 and I need to set a filing deadline milestone at 60 total days after June 1. or July 31, 2016 in this example. However Smartsheet is calculating the filing date milestone as August 25 when I enter it as FF + 60 in the predecessor column, I think because I have setup only Mon-Friday as working dates in my account settings and July 4th is a holiday as well. I don't want to change the working days or holidays settings, but this one particular milestone/deadline has to be based on 60 total elapsed calendar days after it's predecessor.