Can someone please assist with reporting at risk line items? I have parent/child hierarchy and want to only report those parents that are over budget and only the line items under that parent that have fees greater than 0.
Hi,
Can you describe your process in more detail and maybe share the sheet(s) or some screenshots? That would make it easier to help. (share too, andree@getdone.se)
Have a fantastic week!
Best,
Andrée Starå
Workflow Consultant @ Get Done Consulting
There are a few ways to do this. The easiest way would be to use a checkbox column and write an IF statement to establish your criteria. You could then build your report to pull all rows where the box is checked.
=IF(AND(COUNT(CHILDREN([Item Name Column]@row)) > 0, [Actual Cost Column]@row > [Budget Column]@row), 1, IF(AND(COUNT(CHILDREN([Item Name Column]@row)) = 0, [Total Column]@row > 0), 1))
First it will look to see if the row has any children rows. If it does and the Actual is greater than the Budget, it will check the box.
If the row does not have any children rows (meaning it is itself a child row) and the Total is greater than 0, it will check the box.
You can then build your report to pull all rows where the box is checked, and it will automatically be sorted with the parent row above the children rows.
Hey, Is anyone else facing this issue in the approval notifications sent through smartsheet
I have a sheet with a list of customers in one column, and then the following columns are City, Monday, Tuesday, Wednesday, Thursday, Friday. I need help with a formula that I can put in my sheet summary so that if the customer column says Staples (It can say this in multiple rows) that it will tell me the total package…
Hi Smartsheet community, I've always tried to answer questions but this is my first time posting. So I have formula =IF([Project Status]@row = "Complete", 1, 0) set up in the "Complete Check - Hide column" to check the box when the project status is marked complete. The project status column is tied to several other sheets…