Hi there, i would like to start an activity 10 days before either activity A OR activity B starts. How should i define the predecessor? BR Marco
its based off of row numbers. So if A was on row 1 and B was on row 2 you would put
1-10,2-10
exactly like that inside of the predecessors column
Hi Marco,
You can have the same predecessor for more than one task, however there currently isn't a way to define an OR criteria. Please feel free to submit a Product Enhancement Request to let our Product team know that you'd like to have this functionality in Smartsheet.
To represent a period of inactivity or overlap between the predecessor and dependent, you can use lag time. More information on this can be found here: https://help.smartsheet.com/articles/765727-enabling-dependencies-using-predecessors
Hi L@123 and Alejandra
Thank you for your answers. I think I didn't express myself properly - excuse my French
In other words… “Activity C” should start 10 Days before Activity (A or , depending on which Activity starts FIRST! Example “Activity A” starts on May 1, 2019, “Activity B” starts on June 1, 2019. So “Activity C” is scheduled to start on April 20. Maybe you have an idea how to solve this problem. Thanks a lot in advance! Marco
I've created a Smartsheets form. When someone submits the form, I want them to automatically be emailed a document that has resources and links, but the document is filtered to only show the content that corresponds with what they selected in the form. Is something like this possible? What types of documents or automations…
I have a sheet that I created in a previous version, and it had a form. I was recently upgraded to a newer version and now my form is not working. I created a new form for the sheet, and it is giving me an error also. Does anyone know what I can do to fix this? The error says Form Unavailable. Sorry, the form you're trying…
Hi, I have read the post from 8/21/25. I am still getting the same error. I am setting up a new device and just download the latest version as of 9/5/25. I am using a Eunivon Smart White Board for touchscreen capability. It is running Android 14. Any help would be appreciated.