I need help with a formula to automate my RYGGrey. Here are the rules:
If status = complete, grey
If status is in progress or not started and finish is in the past, red
If status is in progress or not started and finish is today + 5 days (within the next 5 days), yellow
If status is in progress or not started and finish is greater than 5 days out, green
Comments
-
Give this a go...
=IF(Status@row = "Complete", "Gray", IF(Finish@row < TODAY(), "Red", IF(Finish@row < TODAY(5), "Yellow", "Green")))
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 62.1K Get Help
- 352 Global Discussions
- 198 Industry Talk
- 427 Announcements
- 4.4K Ideas & Feature Requests
- 133 Brandfolder
- 127 Just for fun
- 127 Community Job Board
- 443 Show & Tell
- 28 Member Spotlight
- 1 SmartStories
- 283 Events
- 36 Webinars
- 7.3K Forum Archives
Want to practice working with formulas directly in Smartsheet?
Check out the Formula Handbook template!
Check out the Formula Handbook template!