I'm using resource allocation to calculate schedule duration but the schedule isn't updating to reflect the allocation.
Why didn't resource allocation (other than 100%) change task duration?
Hi Ami,
At this time, the duration of a task doesn't change based on the values in the Allocation % column, but this would be a great opportunity to submit a Product Enhancement Request to let our Product team know that you'd also like to have this functionality in Smartsheet.
As to the "why", please see Robin Sherwood's comment on this thread: https://community.smartsheet.com/discussion/allocated-time-versus-duration
same issue is for me. It would be smart to let culculatoin of the task duration from two columns like Workload and % Allocation. For example: if workload in 5d and allocation 50% -> Duration should be 10d and this 10d system should take to build Gant.
I have the same issue. It is sad to see that an issue identified in 2015 has not been implemented yet, despite the acquisition of 10,000ft.
Hi, "Fields marked with an asterisk (*) are required." is the very first line in the body of every form I create. I don't remember seeing it before (unless you missed filling out a required field; then you would see the message). Is there a way to turn it off or change it? None of my forms are in English so the message is…
I have a sheet that I pull into a report. The report I then want to use to make a stacked bar chart and put into a dashboard if I can. The columns I am trying to make into a stacked chart are: Lead, project and phase. The issue is that there are several leads and I need the stacked bar chart to show in different colors for…
I have a dynamic view setup for a dashboard that has NO restrictions And on the Sharing tab, I have a Group that I created as the additional share access to the view But the individuals in the Group still cannot see the data from the dashboard. Am I missing something? Because when I share the view to them individually…