Is there a way to set a dynamic column to be the % Complete column for the purpose of setting the Task Completion bar?
All help is appreciated.
Hi Ben,
To accomplish this, open the Project Settings on the sheet and set the % Complete Column drop-down list (under Options) to reflect the column you've assigned as the % Completed Column.
If needed, more information on this can be found in our help article: https://help.smartsheet.com/articles/765737-project-sheet-columns-start-date-end-date-duration-complete-and-predecessors#Complete
I searched the community and did not see a formula that calculated Quarter based on a Start and a Finish date while also accounting for cases where the year for the Start and Finish date differ. The formula below handles that. A few notes … It assumes that Finish is always >= Start. The entire formula is wrapped with…
i am not good with writing formulas within a sheet. I asked the AI tool in the sheet to help me write a formula and I am getting a Circular reference back. I'm trying to have it write the following formula for me. If the column "Tracking #" is not blank, change Column "Deployment Phase" to "Shipped" I have tried adding in…
I have a workflow that detects a row(date) that is changing its Fiscal Week Finish Date and send this row to other Sheet. Long story short: I collect delayed tasks in separate file & I tag reasons for delay for these tasks. It happens that plan are analyzed 2-3 hours and dates are being changed several times. I would like…