Gantt Task Completion bar based on dynamic % Complete
Ben Donahue
✭✭✭✭✭
Is there a way to set a dynamic column to be the % Complete column for the purpose of setting the Task Completion bar?
All help is appreciated.
Tags:
Comments
-
Hi Ben,
To accomplish this, open the Project Settings on the sheet and set the % Complete Column drop-down list (under Options) to reflect the column you've assigned as the % Completed Column.
If needed, more information on this can be found in our help article: https://help.smartsheet.com/articles/765737-project-sheet-columns-start-date-end-date-duration-complete-and-predecessors#Complete
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 63.9K Get Help
- 410 Global Discussions
- 220 Industry Talk
- 458 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 136 Just for fun
- 57 Community Job Board
- 459 Show & Tell
- 31 Member Spotlight
- 1 SmartStories
- 298 Events
- 37 Webinars
- 7.3K Forum Archives
Want to practice working with formulas directly in Smartsheet?
Check out the Formula Handbook template!
Check out the Formula Handbook template!