I'm working with resource allocation across multiple projects. Resource allocation is turned on for the account and then turn on and off for each sheet I want in the overall program.
My understanding is that %allocation is assumed to be at 100% when there's no %allocation column specifying otherwise.
In our projects we use multiple resources assigned to a task.... a lead, a manager, a scientist and a technician, each with their own %allocation for a specific task.
I am able to create the columns and auto-calculate the %allocation based on duration and the work within that duration.
Is it possible to have multiple %allocation columns? and assign one for each resource?