I have tried searching and figuring out what my formula should be, but I just can't get it. I want my flag to be red when there are 3 days or less to due date. Frustrated. See screenshot.
Try something like this...
=IF(TODAY(3) >= [Due Date]@row, 1)
To get it to ignore the flag once the row has been checked as complete, you would use this...
=IF(AND(Complete@row = 0, TODAY(3) >= [Due Date]@row), 1)
That works perfectly! Thank you so very much!
Happy to help!
Hi there, I've created a sheet to where my team is tracking information received. In one column, we are logging the date and time information came in (ie: November 21, 2025 8:30 AM). I would like to add a checkbox column, with a formula specifying that the box be checked if the logged time is AFTER 8:30 AM, and left…
I have a list of properties that I'm keeping track of. I have each building divided into suites (children) and each suite has a cell with its square footage. The total square footage rolls up to the building name. I also have a drop down column that shows if the suite is occupied or vacant. I need a to calculate the…
Hi! I'm fairly new to SmartSheets but have been trying a number of things that havent yet worked. I want to be able to show for each parent row, the number of child rows completed as a %. So for the parent row Process Overview there are 7 tasks and 6 tasks are complete so I want it to show as 90%. Can anyone help me?