Allocating the % of the time can be worked during the day

I am trying to allocate the time that the employee can use for that task during the day to smartsheet.
How can I for example if employee has 8 hours of work to do on one task, but he can only spend 50% of his day to this task. This means it will take him 2 days instead of 1 day since he can only work for 4 hours a day. How can I include this to the smartsheet so that start and finish date will be calculated depended on the result of allocated % and the total days of work the task require.
I want to allocated depending on each task, and not by resources, so resource chart wont work.
This was able to be calculated through MS Project. I am trying to use smartsheet instead of MS Project, but I just can't find this function in smartsheet.
Β
Thank you in advance!
Comments
-
Hi happysatomi,
As you have found, the duration column will not change based on value entered in the allocation % column. When you have a moment, submit aΒ Product Enhancement RequestΒ to let our Product team know that you'd like to have this functionality in Smartsheet.Β
-
Thank you @Alejandra. I assume then that means right now, you cannot input allocation %.Β
If I change it to business version, do you know if I can use allocation% in some kind of the format? Thank you!
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 67.9K Get Help
- 474 Global Discussions
- 208 Use Cases
- 517 Announcements
- 5.6K Ideas & Feature Requests
- 87 Brandfolder
- 157 Just for fun
- 84 Community Job Board
- 521 Show & Tell
- 36 Member Spotlight
- 3 SmartStories
- 309 Events
- 37 Webinars
- 7.3K Forum Archives