Milestone Tracking Report - Numerous projects
Hi all
I'm trying to create a status report which would roll up project tasks and their progress into an easily view-able report and/or widget
The data will be across multiple sheets and I'm trying to find a way to trigger both active, complete and in progress data sets so that I can target the relevant stages inside of the report.
I have attached a screen shot of what I'm trying to get to- Hopefully it makes sense!
Comments
-
Hi Leah,
How is the sheet(s) set up? You'd probably need to collect the information in another sheet (or columns on the same sheet) to get the structure that you want.
Can you describe your process in more detail and maybe share the sheet(s) or some screenshots? (Delete/replace any confidential/sensitive information before sharing) That would make it easier to help. (share too, andree@getdone.se)
Have a fantastic day!
Best,
Andrée Starå
Workflow Consultant @ Get Done Consulting
SMARTSHEET EXPERT CONSULTANT & PARTNER
Andrée Starå | Workflow Consultant / CEO @ WORK BOLD
W: www.workbold.com | E:andree@workbold.com | P: +46 (0) - 72 - 510 99 35
Feel free to contact me for help with Smartsheet, integrations, general workflow advice, or anything else.
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 64.2K Get Help
- 419 Global Discussions
- 221 Industry Talk
- 461 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 141 Just for fun
- 58 Community Job Board
- 462 Show & Tell
- 32 Member Spotlight
- 1 SmartStories
- 299 Events
- 38 Webinars
- 7.3K Forum Archives