Good afternoon
We have resources that we have assigned to tasks for the next few months, booked out. How are we able to see our resources in calendar view?
Hello,
Each bar in the calendar will only display the text from the Primary Column of the sheet or report. It's not currently possible to display any other column in the Calendar View task bar, but this would be a great opportunity to submit a Product Enhancement Request.
As a potential workaround, I would suggest creating a conditional formatting rule that applies a specific color to the task bar based on the person in the contact list column.
If needed, more information on these topics can be found here:
Hi, I'm using smartsheet to track updates on each task in a tracker. These updates may span over a year, so they get lengthy. I was excited about smartsheets because viewing these notes is a lot cleaner. However, I've just realized that there is a content limit to a cell, which is a huge issue. While excel was annoying to…
Hello, i've a question about 2 tasks. Task 1 has for example 4 hours and should be on day 1 for example 6 january. Task 2 has 30 hours and should be on start on 4 january and futher. How can i manage that on 6 january task 2 has only 4 hours? Now i got the message user is over-allocated because task 2 is planned on a full…
Hi All, We have several update automations on various solutions - and have worked very well for getting info from people that dont have smartsheet access - how ever in Sept we switched over to SSO and MFA and activated the Safe Share - We have now run into an issue that when our update automations trigger and people within…