Welcome to the Smartsheet Forum Archives
The posts in this forum are no longer monitored for accuracy and their content may no longer be current. If there's a discussion here that interests you and you'd like to find (or create) a more current version, please Visit the Current Forums.
Planned and Earned Value into Project
Comments
-
Tom,
I am looking for the exact same thing - ie how to show earned value of projects with Smartsheet.
Both schedule and cost.
And generate the curve for reporting.
Let me know if you find anything and I will do the same.
Rob
-
HI Robert,
Good day and thanks for your interest. I have done some of the following work so far..
-Already have my main budget at Completion (BAC)
-My Actual cost numbers come from a weekly report (AC)
-My SS project auto calulates the % Completed
-I created a formula for my Earned Value (EV) %Complete * BAC Example: .50 * $20,000 = $10,000
Still working the more complicated formulas , Thanks, Tom
-
Tom,
Got it and thanks for the reply.
For an Earned Value curves:
Cost Variance is CV = BCWP - ACWP
Schedule is similar with SV = BCWP - BCWS.
Are these typically plotted on the same curve, or 2 separate curves?
I am starting from scratch - did you find a excel or other spreadsheet which can graphically take th evalues and display to a Earned Value Curve?
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 64K Get Help
- 410 Global Discussions
- 220 Industry Talk
- 459 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 137 Just for fun
- 57 Community Job Board
- 459 Show & Tell
- 31 Member Spotlight
- 1 SmartStories
- 298 Events
- 37 Webinars
- 7.3K Forum Archives