Planned and Earned Value into Project

Tom Pettit
edited 12/09/19 in Archived 2016 Posts

Wondering if anyone has done any formulas for either Planned Value (PV), Earned Value (EV), into their SS projects?  I have all the costing,tasks, opex/capex.%Complete,dates.. in my projects and this would be my next step :)

Comments

  • Tom,

    I am looking for the exact same thing - ie how to show earned value of projects with Smartsheet.

    Both schedule and cost.

    And generate the curve for reporting.

    Let me know if you find anything and I will do the same.

    Rob

  • HI Robert,

             Good day and thanks for your interest. I have done some of the following work so far..

    -Already have my main budget at Completion (BAC)

    -My Actual cost numbers come from a weekly report (AC)

    -My SS project auto calulates the % Completed

    -I created a formula for my Earned Value (EV)    %Complete * BAC   Example:  .50 * $20,000 = $10,000

     

    Still working the more complicated formulas :) , Thanks, Tom

     

  • Tom,

    Got it and thanks for the reply.

    For an Earned Value curves:

    Cost Variance is CV = BCWP - ACWP

    Schedule is similar with SV = BCWP - BCWS.

     

    Are these typically plotted on the same curve, or 2 separate curves?

    I am starting from scratch - did you find a excel or other spreadsheet which can graphically take th evalues and display to a Earned Value Curve?