Parent level approval requests?
Is there a way to set up approval requests at the parent level?
Parent row includes project description, Owner, PMO, etc, etc.
Child rows break out task types into groups
Grandchildren row list owners of each task under the task type group.
Example:
Description Owner PMO
- Project XXX Jon Doe Pam PMO (Parent row)
- Requirements (child group 1)
- Requirements Pam PMO (grandchild row)
- Test scripts Jason Jones (grandchild row)
- Development (child group 2)
- Development Chris Smith (grandchild row)
- Unit Test JJ Johnson (grandchild row)
We use same Owner column for parents & grandchildren. I would like to set up a notification & an approval request at the parent level for the project Owner when all of the tasks are completed. I really don't want to add another column. I have a bunch of hidden columns already and would like to minimize if possible.
Thanks ahead of time,
Angie
Comments
-
Hi Angie,
What other columns are you using at the moment? It might be possible to use them to accomplish what you need.
Can you describe your process in more detail and maybe share some screenshots? (Delete/replace any confidential/sensitive information before sharing) That would make it easier to help.
Have a fantastic week!
Best,
Andrée Starå
Workflow Consultant @ Get Done Consulting
SMARTSHEET EXPERT CONSULTANT & PARTNER
Andrée Starå | Workflow Consultant / CEO @ WORK BOLD
W: www.workbold.com | E:andree@workbold.com | P: +46 (0) - 72 - 510 99 35
Feel free to contact me for help with Smartsheet, integrations, general workflow advice, or anything else.
-
Hi Andrée,
This may be overkill, but thought it may be helpful. Here is a list of all of my columns. Hidden have purple text. It explains each column and what level it is. I also have a screenshot that shows 3 views. Parent row rolled up, Parent & dhild rows, Parent, child, and grandchild rows.
If there's anyway to figure out how to use Owner at Parent level to get approvals, it would be great.
Thanks!
Angie Hatfield
-
Happy to help!
What formula do you have in the Ancestors formula?
SMARTSHEET EXPERT CONSULTANT & PARTNER
Andrée Starå | Workflow Consultant / CEO @ WORK BOLD
W: www.workbold.com | E:andree@workbold.com | P: +46 (0) - 72 - 510 99 35
Feel free to contact me for help with Smartsheet, integrations, general workflow advice, or anything else.
-
=COUNT(ANCESTORS(Project1132))
Let me know if you want the rest of them.
Thanks again!
-
Maybe you could use a combination of the COUNT of the ANCESTORS and the percent complete.
Would that work?
SMARTSHEET EXPERT CONSULTANT & PARTNER
Andrée Starå | Workflow Consultant / CEO @ WORK BOLD
W: www.workbold.com | E:andree@workbold.com | P: +46 (0) - 72 - 510 99 35
Feel free to contact me for help with Smartsheet, integrations, general workflow advice, or anything else.
-
Hi Andrée,
I think that will work! I should have thought of that. I really appreciate you taking a look at this and finding a solution.
Have a great week!
-
Excellent!
I'm always happy to help!
Have a fantastic week!
SMARTSHEET EXPERT CONSULTANT & PARTNER
Andrée Starå | Workflow Consultant / CEO @ WORK BOLD
W: www.workbold.com | E:andree@workbold.com | P: +46 (0) - 72 - 510 99 35
Feel free to contact me for help with Smartsheet, integrations, general workflow advice, or anything else.
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 63.9K Get Help
- 410 Global Discussions
- 220 Industry Talk
- 457 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 136 Just for fun
- 57 Community Job Board
- 459 Show & Tell
- 31 Member Spotlight
- 1 SmartStories
- 298 Events
- 37 Webinars
- 7.3K Forum Archives