Hi,
I've read through a few threads and I am unable to re-create a simple countdown formula. I keep getting an #INVALID OPERATION error.
Am I missing something? Please help! Thank you!
Are both the Target Date and Today formatted as Date column types?
Have a fantastic day!
Best,
Andrée Starå
Workflow Consultant @ Get Done Consulting
Yes, both columns are Date types.
That's strange!
It should work.
Try to change the columns to text and back again and also try to edit the formula and then change it back again. Maybe it's a glitch.
Did it work?
Yes!! That fixed it!! I seriously thought I was going crazy!
Thank you so much for your suggestion, I knew it had to be something simple!
Excellent!
Happy to help!
(I starred at it for a long time as well)
I am wanting to calculate Netdays but only if there is data in 'Corrective Action 1' I am currently using this formula: =IF(ISBLANK([Date Action 1 Complete]@row ), NETDAYS([Date of Event]@row , TODAY()), NETDAYS([Date of Event]@row , [Date Action 1 Complete]@row )) How do I adjust it to only pull a date when Corrective…
I've set up a Smartsheet that sends an approval request to a vendor to accept the terms of employment (outlined in a PDF generated with information from the sheet). They are not required to sign the document, just click Accept or Reject. While the contract (PDF) is attached to the row, and while I would have a date in the…
I have Concept phase projects that can result in multiple Phase 1 projects being generated from one Concept Review. I want to calculate the time in the Concept Phase for the first project from that Concept (the Approved Gate 0 UID), but mark it N/A for any subsequent references to that UID. I figured out the formula below…