I have logged in today and all the dates in different columns are coming up in US format mm/dd/yy.
Not had this issue before, I have been through my settings and region is correct but to no avail.
Anyone have a fix for this?
Hi Nicholas,
There seems to issues with date formats at the moment. I've had a few client's reach out with issues and I've also seen issues from others in the community.
If you're experiencing issues and If you haven’t already, I would recommend that you reach out to the Smartsheet Support Team. https://help.smartsheet.com/contact
Hope that helps!
Have a fantastic day!
Best,
Andrée Starå
Workflow Consultant @ Get Done Consulting
My team in EU mentioned this issue. They did find a way to correct it by clearing the cache and resetting the time zone in Smartsheet personal settings.
Excellent!
Thanks for sharing!
Testing now!
Is anyone still having these issues? Having this problem from Melb, AUS. How long does smartsheet typically take to respond to service tickets?
Hi @Clair Henneberry
Can you be more specific about your issue?
Even if your own preferences are set to a specific date format, could you be viewing a report that was created by someone with a different date setting? Or is it possible that the owner of the sheet applied standardized date format settings? (See here: https://help.smartsheet.com/articles/2479481)
I have a monthly report I send out that has a long list of recipients. I know I can edit the recurrence of it being sent, but does anyone know of an easy way to just add or take out people that get my email without having to recreate the whole thing?
We would like to allow conference attendees to check themselves in using tablets at the conference center. I know there is a "find in sheet" magnifying glass in table view, but it is not super obvious, especially for non-Smartsheet users. Is there a better way for them to easily find their row among all the attendees so…
Greetings- I have a automation setup when I select the "status" column drop-down to "completed" I want the row info to be emailed to the contact to submitted it with a follow up then I want it to archive the row (aka move to another sheet). When I run the automation only 1 of the 2 requests happen. The archive happens…