How can I get sheets to remain in the workspace/folder when bulk transferring a user's sheets to someone else?
Hi Just Jean,
If the person who you're bulk transferring sheets to is shared to the workspace, items in the workspace will remain in that workspace. However, if the new owner isn't shared to the workspace they'll see transferred sheets, reports, and dashboards in Home in their left panel in a folder named Transferred from [email address of previous owner].
I realize our help center article doesn't mention the workspace aspect of this, so I submitted a request to add this information here: https://help.smartsheet.com/articles/520103-change-the-owner-sheet-report-dashboard
Hi, I'm in the midst of a Smartsheet trial and would like to understand how to set up a project schedule that uses a firm delivery deadline. I understand I could use Start-to-Finish relationships, but this disallows use of many to one predecessor relationships (multiple tasks that are gated by a single work item). I would…
I have a sheet that has a good number of automations that populate a field based on a value changing in a cell. These same automations have been working just fine since March up until today. All of a sudden they are being triggered when there is no change to the cells in question. If I click into the cell history, it…
I need to add multiple columns to a project using Global Update. I only see an option in Control Center to add a single column, one at a time. Can anyone tell me if what I'm trying to do is possible, and how to proceed?