I accidentally drug a line to link two tasks, they are not dependent on each other. How do I remove the predecessor line?
Go to the predecessor column and remove the number that references the row that is incorrectly linked.
Connor
I am already an Admin of a workspace, but when I enter the sheet to edit, it prompts me that I am a viewer. Has anyone encountered this situation? In the share tab, it shows that I am both an Admin and a viewer. How could a product from such a large company have such a BUG?😫
The black arrow indicates when (around 4:30pm) the mistake was made. I would like to recover a previous version say around 2pm.
I have two identical projects with the exact same data, but the % Complete in Smartsheet is 14% and the % Complete in Microsoft Projects is 4%. Which one is correct