Sign in to join the conversation:
I want to populate the % Percent field with 100 when the Actual End Date is entered. I tried this formula but I get an error.
=IF([Actual End Date]@row > "0", "100", "0")
Any suggestions?
Hi Dee,
Try this.
=IF(NOT(ISBLANK([Actual End Date]@row)), 1)
Hope that helps!
Have a fantastic weekend!
Best,
Andrée Starå
Workflow Consultant / CEO @ WORK BOLD
To add because I can't edit: Have a fantastic week!
Thank you and it works when I turn off % Complete in Project Settings. But then it wont calculate overall project % complete. I am stuck.
Happy to help!
Unfortunately, you can't have both.
You'd have to disable the automatic % Complete feature and add manual formulas instead.
Would that work?
Another option could be a third-party integration like Zapier or the Smartsheet API. Is that an option?
I am getting blocked with edits again as well... -_-
Yes, i get sometimes now as well.
It's back!
HAHAHAHAHAHAHAHAHA!!!!!!!!!!!
Hi Community I have a check box column with a column formula to check if the Start Date and End Date are Todays Date. =IF(AND(ISDATE([Start Date]@row ), ISDATE([End Date]@row ), [Start Date]@row <= TODAY(), [End Date]@row >= TODAY()), 1, 0) This works when there is a date range, ie Start Date is 18/2/26 and End Date is…
I'm new to Smartsheets and attempting to transfer tracker data from Google Sheets to build dashboards. I use emojis in trackers and COUNTIF formulas to summarize the data based on emoji categories. The formulas work as long as there is no other data in the cell but I get a "0" if there is any other text in the cell. Please…
I’m trying to build a formula that can achieve the following logic, but I’m struggling to get it working correctly. I have a data sheet with around 100 project rows. Each row contains a Fab Start date and a Fab Finish date (along with many other fields). Some projects run across two consecutive months. In my metrics sheet,…