Sign in to join the conversation:
I want to populate the % Percent field with 100 when the Actual End Date is entered. I tried this formula but I get an error.
=IF([Actual End Date]@row > "0", "100", "0")
Any suggestions?
Hi Dee,
Try this.
=IF(NOT(ISBLANK([Actual End Date]@row)), 1)
Hope that helps!
Have a fantastic weekend!
Best,
Andrée Starå
Workflow Consultant / CEO @ WORK BOLD
To add because I can't edit: Have a fantastic week!
Thank you and it works when I turn off % Complete in Project Settings. But then it wont calculate overall project % complete. I am stuck.
Happy to help!
Unfortunately, you can't have both.
You'd have to disable the automatic % Complete feature and add manual formulas instead.
Would that work?
Another option could be a third-party integration like Zapier or the Smartsheet API. Is that an option?
I am getting blocked with edits again as well... -_-
Yes, i get sometimes now as well.
It's back!
HAHAHAHAHAHAHAHAHA!!!!!!!!!!!
my formula is returning number of dates, as in adding dates.
Disregard. The problem was additional dates on collapsed child rows. Thank you. Good afternoon. I have created a metric sheet that was then used to create a chart. The formula is written as: =COUNTIF({Date of Visit}, IFERROR(YEAR(@cell ), 0) = Year@row ) This was then drug down for 4 rows. Rows 1, 2, and 4 have the correct…
My goal is to have the percentage update automatically each day. If the task has a duration of 45 days and we are 3 days in, I need it to show the percentage complete. It would cap at 100% once it has reached the end date