Resource Planning 'Go Live' Marker
Options

Louise Jones
✭✭
Hi - If i had a gantt chart and my project runs for 4 weeks but 2 weeks in is go live and 4th week is transition, is there a way to put a marker on the line like a diamond or something please
Thanks
Comments
-
Louise,
Create a Task called GO LIVE set the date and set dration to 0 days.
Alternativly link the GO LIVE Task to the last task to happen before GO LIVE with a Finish to Start Link.
James