Need a way to identify tasks on my workplan where the actual lag time is different from the standard lag time.
My workplan includes:
1. Predecessor column (includes predecessor with +/- lag)
2. A separate text column "Standard Lag Time "
Whenever the lag time needs to be changed the predecessor column is updated. The Standard Lag Time column is never changed as it serves as a reference.
How can I have Smartsheet format (e.g. highlight) predecessor cells whenever the lag time is different from the Standard Lag time?