I have checked all of my settings in the main sheet and dependencies are not turned on nor predecessors, the box remains grey? I also have ensured that in the details panel, it is not read only.
By any chance is the finish date calculated by durations based on a start date or by a formula? I don't have the dynamic view, but in reports when a field is calculated with formulas it is uneditable.
Mike is correct. Also, make sure the date column is not locked in the main sheet.
If the finish date is assigned in the dependencies settings in the Gantt View then you will not be able to change it. I think that is the case even if the dependencies check box is not checked.
Hi Marc,
Is it the same for all rows? Are you using any Field Logic rules?
I hope that helps!
Have a fantastic week!
Best,
Andrée Starå
Workflow Consultant / CEO @ WORK BOLD
Thanks This was driving me crazy!! once I Changed the date to another date column in dependencies (although not active) it worked.
Company uses Bluebeam Revu software to create drafting check sessions (adding notes to PDF's). These session come from the same email address every time and can be automated to be sent to an email. I want to try and get these emails to go to a smartsheet row. what would be the best way to achieve this? My company uses…
I have a DataTable that is currently populated by a DataShuttle. When I upload the source report to a sheet, the data gets added into the DataTable via DataShuttle. The DataShuttle is configured to "add rows when added to the source file" and "update rows as they change in the source file". The unique column identifier is…
Dear Smartsheet Community, Our organisation operates on the Smartsheet AU Region instance to meet local data residency and compliance needs. While we appreciate the capabilities the AU instance offers, we have received late breaking business requirement in terms of features/functions that are available in the US region but…