Hi all,
I would like to manage my projects from resource views, but I can not enable this feature (enterprise plan).
I am not the system admin. Is it it possible that he could give me the rights to manage my resources and views?
Thanks
Yes. A sys admin can grant rights to resource views. You would also need each of the other users to have them included in the resource view. For example...
John Doe wants to include Jane Smith in a project and have her in his resource view.
Not only would John Doe need access to resource view, but so would Jane Smith.
Thanks,
it means, that John cannot add jane by itself but has to ask the system admin to add Jane?
Not very comfortable in an enterprise organisation :-(
That is correct. For John to see Jane, both John and Jane need to have resource view turned on. Fortunately, turning on or off Resource View for a user is as simple as checking or unchecking a box for the Sys Admin.
They have 2 options.
1. If it is just a few people, it may be easier to just search them individually in the User Management window directly.
2. If it is a large group, there is an option to "bulk update". The appropriate steps for which are outlined when "Bulk Update Users" is selected from the "More Actions" dropdown in the User Management window.
I am attempted to export to excel. I have two different smartsheet documents to export. One of them exported to excel fine, but not the other. This happened a few weeks ago. I make sure all columns were the correct size & no cells were hidden. "We have found a problem with (file) Do you want us to try and recover as much…
Hello Smartsheet Community, I need some help with a report that I created and shared with a customer. The customer is not seeing any of the information that is pulling into the report. See screen shot below that the customer texted me. I do have the report filter only showing the customer their product pulling from our…
BLUF: When I create an Invoice, I need the cell-link to my live price data to be severed. I currently have a Price sheet for my products that is updated frequently. I use Control Center to create Projects, which includes an Invoice sheet. I have a dropdown on my invoice sheet to select a product, and then I use Index…