I want to be able to use a dependency like "either/or" instead of "and"
ie: Task 3 can start after either Task 1 or Task 2 is finished, but does not require both tasks to be done.
Is this possible?
=if(or([Task 1]@row = "Finished",[Task 2] = "Finished"),1,0)
Thanks for the reply, but this seems to be saying "if task 1 is complete, task 2 is also complete" but that wouldnt be the case.
Task 1 and 2 wont be completed at the same time. But one of them needs to be done before Task 3.
I misunderstood, you mean how to set the predecessors on a project sheet then right?
Yes. I can make it use both predecessors, but I want it to use one *or* the other.
Someone may correct me if I am wrong, but I am fairly confident you are unable to do that currently in smartsheet. There is not mention of it in the official documentation. I recommend submitting a product enhancement request via the link on the right side of the community webpage.
https://help.smartsheet.com/articles/765727-enabling-dependencies-using-predecessors
I've created a Smartsheets form. When someone submits the form, I want them to automatically be emailed a document that has resources and links, but the document is filtered to only show the content that corresponds with what they selected in the form. Is something like this possible? What types of documents or automations…
I have a sheet that I created in a previous version, and it had a form. I was recently upgraded to a newer version and now my form is not working. I created a new form for the sheet, and it is giving me an error also. Does anyone know what I can do to fix this? The error says Form Unavailable. Sorry, the form you're trying…
Hi, I have read the post from 8/21/25. I am still getting the same error. I am setting up a new device and just download the latest version as of 9/5/25. I am using a Eunivon Smart White Board for touchscreen capability. It is running Android 14. Any help would be appreciated.