Forcing a Task Start Date Causes Over Allocations

I'm a fairly new SS user, but have experience with MS Project. I have a task that, based on predecessors starts on a date that is earlier than when a shared resource is available. What is the best practice for assigning a "forced" start date?
When I attempt to force this one start date on a single task, the result is several over allocations. Does SS not recalculate the timeline based on remaining predecessors? Why does it choose to over allocate the resources instead of recalculating the sheet to match the resource availability?
Answers
-
Hi Terry,
I believe this is called a "constraint" in Microsoft Project. If so, constraints in Smartsheet are not currently supported, but this would be a great opportunity to submit a Product Enhancement Request.
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 67.1K Get Help
- 448 Global Discussions
- 154 Industry Talk
- 504 Announcements
- 5.4K Ideas & Feature Requests
- 85 Brandfolder
- 156 Just for fun
- 80 Community Job Board
- 513 Show & Tell
- 34 Member Spotlight
- 2 SmartStories
- 308 Events
- 36 Webinars
- 7.3K Forum Archives