Gantt Chart and Resources

Good evening,
Looking to see if someone can point me in the right direction?
We are a fabrication facility that has resources both human and robotic. We are looking to track projects as they come thru our fabrication shop but we need to enable the resources to be allocated to the following amount of time per week
Python: 50 HRS a week
Fit up and Weld: 250 HRS a week
Paint and Load: 100 HRS a week
How do i go about doing this?
I have added the contact email for each of the three resources above but cannot locate where I can set their available hrs a week?
Thank you
Answers
-
Hi @BESP10,
It's not currently possible to set the number of available hours per resource per week within Smartsheet. However, you can accomplish this with 10,000ft, a resource management platform that has been recently acquired by Smartsheet.
If needed, more information on 10,000ft can be found here: https://help.smartsheet.com/learning-track/best-practice-webinars/elevate-your-resource-management-10000ft
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 66.1K Get Help
- 430 Global Discussions
- 149 Industry Talk
- 490 Announcements
- 5.2K Ideas & Feature Requests
- 85 Brandfolder
- 154 Just for fun
- 74 Community Job Board
- 499 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 305 Events
- 36 Webinars
- 7.3K Forum Archives