Adding dependencies halfway through the timeline
Greetings,
Are there another dependencies apart from the four inbuilt ones (SS,FF, SF,FS) ?
I need to link milestones halfway through some of the tasks.
For example : If task A takes place over 10 days and on the 3rd day, there a milestone to be reached, how do we create the dependency between the two ?
Thank You
Answers
-
You would have to have separate tasks to achieve that
Milestones are 0 day tasks
✅Did my post help answer your question or solve your problem? Please help the Community by marking it as the accepted answer/helpful. It will make it easier for others to find a solution or help to answer!
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 63.9K Get Help
- 410 Global Discussions
- 220 Industry Talk
- 457 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 136 Just for fun
- 57 Community Job Board
- 459 Show & Tell
- 31 Member Spotlight
- 1 SmartStories
- 298 Events
- 37 Webinars
- 7.3K Forum Archives