Adding dependencies halfway through the timeline

Greetings,

Are there another dependencies apart from the four inbuilt ones (SS,FF, SF,FS) ?

I need to link milestones halfway through some of the tasks.

For example : If task A takes place over 10 days and on the 3rd day, there a milestone to be reached, how do we create the dependency between the two ?


Thank You

Answers

  • Frank Falco
    Frank Falco ✭✭✭✭✭✭
    edited 02/13/20

    You would have to have separate tasks to achieve that

    Milestones are 0 day tasks


    ✅Did my post help answer your question or solve your problem? Please help the Community by marking it as the accepted answer/helpful. It will make it easier for others to find a solution or help to answer!