Avoid Overallocation

DanCaparroz
DanCaparroz ✭✭
edited 02/21/20 in Smartsheet Basics

Hello,

I have a project that I want to undersand where the go-live date would go based my actual capcticy of resources without overallocating them. Is that possible to do ?


So, if someone is 200% the start/end time of one of the tasks would changed to avoid it (still respecting its predecessors). I have tried to put a lower allocation % but the final date is not being calculated.. so if a task ahs 8h with a 8h working days and the resource is 50% to it, it would take 2 days for that task and it still being 1 like if he was 100%.


Im talking about the same project, not cross project.

Answers