Hello everyone,
We're using gantt charts to planify our tasks. When creating task groups and sub-tasks, the number of days displayed in the task group does not reflect the actual number of days planned but the time span from the beginning of the first task to the end of the last task. This creates confusion when presenting the chart to our customers.
Example:
Group Interal Tasks 102 days Start 19/09/16 End 07/02/17 12%
--> Sub Task Migration 4h 19/09/16 19/09/16 100%
--> Sub Task Documentation 2d 05/12/16 06/12/16 0%
--> Sub Task Server setup 1d 07/02/17 07/02/17 0%
As you can see, the tasks are wide spread on the timeline and instead of counting a total of 3.5 days it shows 102 days (from beginning to end).
Is there any way to show the sum of the actual days?
Thanks for your help,
Stefan