I am developing as schedule that has two sets of start and finish dates namely: Planned Start & Finish vs Actual Start & Finish. Each has its own duration namely planned duration and actual duration. The predecessors are the same for both planned and actual dates. I cannot seem to get the predecessor column to automatically populate both sets of start dates. Only the one duration column is able to automatically update the Finish date. Is it possible to have the dependency functionality for two sets of dates ?

I hope this makes sense. Please see screenshot below.


Best Answer

Answers

  • Hi Debbie

    Thank you for your response, much appreciated.