Split 1 task in 2 periods of time
Dear all
Can I split a task in 2 or more periodes ofo time?
So, task 1 start in week1. On week 2 stop (so nothing to show on gantt). On week 3 finish, all do it in 1 task
Regards
Best Answer
-
You would have to have each block on it's own row. There currently is not a way to show two separate date sets on the same row within a Gantt. Feel free to Submit a Product Enhancement Request when you are able though.
Answers
-
You would have to have each block on it's own row. There currently is not a way to show two separate date sets on the same row within a Gantt. Feel free to Submit a Product Enhancement Request when you are able though.
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 63.5K Get Help
- 402 Global Discussions
- 213 Industry Talk
- 450 Announcements
- 4.7K Ideas & Feature Requests
- 141 Brandfolder
- 135 Just for fun
- 56 Community Job Board
- 454 Show & Tell
- 31 Member Spotlight
- 1 SmartStories
- 296 Events
- 36 Webinars
- 7.3K Forum Archives