Delays to show in GANTT
Hi,
I managed to create a column which contains the formula to count my project delays of scheduled finish vs. actual finish. I used this formula:
=NETWORKDAY([Planned Finish]1, [Actual Finish]1)
How can I show this in the actual GANTT bars so it's made visible?
Thanks!
Answers
-
Hi @lamersrob
The Gantt chart currently is only able to display one set of Start/End dates. Please submit an Enhancement Request when you have a moment!
Thanks,
Genevieve
-
Hi,
Has this been implemented in the meantime?
-
Hi @Klefisch
You can add a Baseline to a Project Sheet which includes two more date columns on a sheet and shows an extra line in that row in the Gantt view, see: Keep Your Projects on Track with Baselines
Other than that, no, Gantt charts can only take one Start and Finish date each per row.
Cheers,
Genevieve
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 63.4K Get Help
- 394 Global Discussions
- 213 Industry Talk
- 449 Announcements
- 4.6K Ideas & Feature Requests
- 141 Brandfolder
- 132 Just for fun
- 131 Community Job Board
- 453 Show & Tell
- 30 Member Spotlight
- 1 SmartStories
- 293 Events
- 35 Webinars
- 7.3K Forum Archives