I want to create individual reports to update a single Project Plan

I have a single project plan with several people responsible for updating the dates. To allow them to JUST focus on their parts, I have created reports by individual name that bring in all the tasks they are responsible for. However, when it comes to changing dates, if they change the duration, it doesn't change the Finish date. I do have dependencies on and predecessors and duration are associated to the Start and Finish columns. Why am I not able to update child task dates (I get not being able to update parent tasks) and have the calculations work? NOTE: the sample reports I am using do not have any predecessors loaded.