Can I hide the weekend days for a task?

I have a task that spans a weekend. It does the correct calculation for the correct number of working days, but in the calendar it's a bit misleading for our team. It makes it appear as if the task is being worked on during the weekend. I would rather have it only displayed for the 'working days' per the calendar settings.

I know a workaround is to create two tasks but that breaks all the dependencies. The calendar display is the critical aspect of this project.