I am a little confused and unsure if I am configuring this feature correctly. I have a Smartsheet with a Contact, Status, and Entry Date columns. My goal is to have a reminder automatically sent, beginning on Entry Date, and then every three days thereafter, if the Status=In Progress to the Contact listed the column.

  1. Do I have this configured correctly?
  2. Will the automation look at earlier (back to 1/1/20) and send reminders for those still "In Progress?"
  3. Is there a way to trigger a workflow like this manually, so that I can test?


Thank you for your help. The community has been so helpful!



Best Answers

  • Mary_A
    Mary_A ✭✭✭✭✭✭
    edited 05/07/20 Answer ✓

    @Donna T You should use a Custom for setting up how often:


    1. ^^ try that.
    2. Yes, the automation runs against all the rows every three days.
    3. So, if the sheet is already in use for a project, you might want to make a copy and test with that instead. In your sheet copy, add your name to Contact column. Then, setup a more frequent time hourly and wait for it to run.
  • Donna T
    Donna T ✭✭
    Answer ✓

    Thank for detailed graphic confirming I had it correct. Much appreciated!

Answers

  • Mary_A
    Mary_A ✭✭✭✭✭✭
    edited 05/07/20 Answer ✓

    @Donna T You should use a Custom for setting up how often:


    1. ^^ try that.
    2. Yes, the automation runs against all the rows every three days.
    3. So, if the sheet is already in use for a project, you might want to make a copy and test with that instead. In your sheet copy, add your name to Contact column. Then, setup a more frequent time hourly and wait for it to run.
  • Donna T
    Donna T ✭✭
    Answer ✓

    Thank for detailed graphic confirming I had it correct. Much appreciated!