Sign in to join the conversation:
The posts in this section are historical and no longer monitored for accuracy. If this discussion interests you and you'd like to join in, please visit the active Community to post and engage.
Is it possible to make individual lines 'Calendar Days' rather than working days? - I have investigated into the project settings and it appears that the calendar dates can only be amended if it changes the whole project? Any advice would be much appreciated.
The working days are indeed per sheet.
So, I don't think so, but can you elaborate on what you want?
Craig
Hi Craig,
Thank you, I believe you have confirmed that working days are per sheet. Can you clarify that if I was to have working days with the exception of 3 lines as calendar days this would not be possible?
Kind regards.
Gabriella,
Yes, there are no per line exceptions.
HOWEVER:
If what you are looking for is to have a task in a project occur on a non-working day, take a look at the "e" (elapsed) option for durations
https://help.smartsheet.com/articles/765737-project-sheet-columns-start-date-end-date-duration-complete-and-predecessors#Duration
Hope this helps.