Welcome to the Smartsheet Forum Archives
The posts in this forum are no longer monitored for accuracy and their content may no longer be current. If there's a discussion here that interests you and you'd like to find (or create) a more current version, please Visit the Current Forums.
Calendar Day Settings

Is it possible to make individual lines 'Calendar Days' rather than working days? - I have investigated into the project settings and it appears that the calendar dates can only be amended if it changes the whole project? Any advice would be much appreciated.
Comments
-
The working days are indeed per sheet.
So, I don't think so, but can you elaborate on what you want?
Β
Craig
-
Hi Craig,Β
Β
Thank you, I believe you have confirmed that working days are per sheet. Can you clarify that if I was to have working days with the exception of 3 lines as calendar days this would not be possible?
Β
Kind regards.Β
-
Gabriella,
Β
Yes, there are no per line exceptions.
HOWEVER:
If what you are looking for is to have a task in a project occur on a non-working day, take a look at the "e" (elapsed) option for durations
Β
Β
Hope this helps.
Β
Craig
Β
-
Gabriella,
Β
Yes, there are no per line exceptions.
HOWEVER:
If what you are looking for is to have a task in a project occur on a non-working day, take a look at the "e" (elapsed) option for durations
Β
Β
Hope this helps.
Β
Craig
Β