Calendar Day Settings
Comments
-
The working days are indeed per sheet.
So, I don't think so, but can you elaborate on what you want?
Craig
-
Hi Craig,
Thank you, I believe you have confirmed that working days are per sheet. Can you clarify that if I was to have working days with the exception of 3 lines as calendar days this would not be possible?
Kind regards.
-
Gabriella,
Yes, there are no per line exceptions.
HOWEVER:
If what you are looking for is to have a task in a project occur on a non-working day, take a look at the "e" (elapsed) option for durations
Hope this helps.
Craig
-
Gabriella,
Yes, there are no per line exceptions.
HOWEVER:
If what you are looking for is to have a task in a project occur on a non-working day, take a look at the "e" (elapsed) option for durations
Hope this helps.
Craig