Is there a formula I can use to have my end date calculated by the start date and duration column?
My duration is in hours.
Answers
-
Smartsheet does not currently calculate time. It can be done, but the exact solution will depend on a handful of details.
HERE is a thread that has links to some time based solutions. Feel free to browse them and let me know on this thread if you have any questions. If you do not find what you are looking for, I'd be happy to list out a few questions that need answered and try to help you with a solution.
-
@Paul Newcome those solutions did not answer my question. I need to know how to calculate the end date based on the Duration Hours per task and the start date of the task.
-
OK. Since none of those worked for you...
Are you assuming 24 hour days so that if your duration is 24 then you advance to the next day or are you working with maybe 8 hour days where a duration of 24 would advance you by three days?
Are you wanting to skip weekends?
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 63.9K Get Help
- 410 Global Discussions
- 220 Industry Talk
- 458 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 136 Just for fun
- 57 Community Job Board
- 459 Show & Tell
- 31 Member Spotlight
- 1 SmartStories
- 298 Events
- 37 Webinars
- 7.3K Forum Archives