Automated Cells to Drive Gantt Charts
Im am trying to setup a gantt chart for for our production department but am hiving some trouble figuring out how it works. We dont typically use start/end dates but rather work with estimated hours for a project. What ive noticed is that the Gantt chart cant be driven by a calculated cell when dependencies are on. is this correct?
We drive our other charts based on total estimated time to complete a project, say 500 hrs, then assign workers at 8 hours per day shifts and have a column for OT hours we will work on that job.
The formula (Est Hours)/((Assigned Workers * 8)+ OT Hours) gives us an estimated end date. I would like to drive the finish date of the gantt chart with this calculated number while also using dependencies. Is this possible?
Answers
-
Hi @Rgioffre
You are correct: when dependencies are enabled, the Date columns used in Project Settings are unable to host formulas. You can read more about this in our Help Center (see here).
To answer your second question, this means it's not possible to have the finish date of the gantt chart be calculated by your formula while also using dependencies. Please submit an Enhancement Request when you have a minute!
Cheers,
Genevieve
Need more help? 👀 | Help and Learning Center
こんにちは (Konnichiwa), Hallo, Hola, Bonjour, Olá, Ciao! 👋 | Global Discussions
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 64.8K Get Help
- 434 Global Discussions
- 138 Industry Talk
- 470 Announcements
- 4.9K Ideas & Feature Requests
- 129 Brandfolder
- 148 Just for fun
- 65 Community Job Board
- 486 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 300 Events
- 36 Webinars
- 7.3K Forum Archives