Need to be able to change Start and End Dates (linked to predecessors) on a report
I see that this topic was open last year, but the thread was closed quoting a workaround--add the duration column to the report and have users modify it to get the desired end date. My project plans need dependencies enabled but I also need users to be able to change the dates in their "My tasks" view. Is there a way to allow this functionality?
Answers
-
Hi @Niyati Kumar ,
It's still not currently possible to change End Dates directly from a Report with dependencies enabled on the source sheet. Start dates that don't have Predecessor values listed on the row can be modified from a report but if you're using Predecessors on a row, the only way to change the Start and End date at this time would be to change the Duration value. More information on this can be found here: https://help.smartsheet.com/articles/522214-creating-reports#toc-modify-an-existing-report
If you haven't already done so, I highly recommend submitting a Product Enhancement Request for making Start and End dates fully editable from Reports as it's possible we may see this implemented in a future release down the road.
Thanks,
Ben
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 64.8K Get Help
- 434 Global Discussions
- 138 Industry Talk
- 470 Announcements
- 4.9K Ideas & Feature Requests
- 129 Brandfolder
- 148 Just for fun
- 65 Community Job Board
- 486 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 300 Events
- 36 Webinars
- 7.3K Forum Archives