Formula for red flag if 3 conditions are met
Formula to use red flag if : Is Milestone is checked, the Planned End Date is today or in the past, and Done is not checked
Tried the below but its not working
=IF(AND([Is Milestone]:[Is Milestone], 1, [Planned End Date]:[Planned End Date], @cell >= TODAY(), Done:Done, 1), 1, 0)
Answers
-
Try this
=IF(AND([Is Milestone]@row = 1, [Planned End Date]@row <= TODAY(), Done@row = 0), 1, 0)
-
Thanks!