Welcome to the Smartsheet Forum Archives
The posts in this forum are no longer monitored for accuracy and their content may no longer be current. If there's a discussion here that interests you and you'd like to find (or create) a more current version, please Visit the Current Forums.
Formula to calculate start date, from end date
Comments
-
Try
= [Start Date]1 - 45
-
Hi Benjamin,
This is what I entered:
=[CONTRACT WRITING]38 - 45
This yields an #INVALID OPERATION
Both columns are in date format.
Thanks
-
I have fixed it - thanks
-
R.
I have set up this exact situation and I don't seem to be having a problem. Are cell links involed or have you converted the data in "CONTRACT WRITING" to a string through another formula calc?
This is the interaction I see
This discussion has been closed.
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 64.8K Get Help
- 437 Global Discussions
- 138 Industry Talk
- 470 Announcements
- 4.9K Ideas & Feature Requests
- 129 Brandfolder
- 148 Just for fun
- 65 Community Job Board
- 486 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 300 Events
- 36 Webinars
- 7.3K Forum Archives