I need to write a formula for counting active projects that are past due for a current month based on schedule complete date being in that current month and when actual complete date is blank.
Project Status = Active
Schedule Complete Date = 7.1.20 - 7.31.20
Actual Complete Date = Blank
Here is the data and fields I would be using. So in this screen shot the result would return 1 for July 2020 since the scheduled complete date was 7.6.20 but the project doesn't have an actual complete date.