Main task shows 99% but all Sub-Tasks are 100%?
Options
I've completed all the sub-tasks for a task and put them all to 100% and marked them Complete. The main tasks still shows 99% though. I've went back over the tasks and entered them as 100% again, but it still doesn't show. I've marked a sub-task down to zero, and the main task drops according. But, when I put the sub-task back to 100...the main task still shows 99%?
Answers
-
Never mind...I went back over it and found 1 task that didn't have any value at all....once I filled that in, it worked fine.
-
Hi Dave,
Thanks for posting your solution! I'm glad you figured out what was going on. 🙂