How do I get Smartsheet to update all dates in project when I change Start date?
Working on year long TI construction schedule and start date is constantly changing due to contract negotiation reasons and others. Having all dates auto update by changing start date will save a lot of time. Thanks!
Answers
-
Hi Kris, I have achieved that in my sheets. We have quarterly classes that we put on, but the steps and timeline are all the same. I achieved this through the predecessor column.
The instructor enters their class date in the green field (that is Row 17) - so I use "lead and lag" rules to populate for each week's set of tasks. 17SS -4w simply means, look at row 17, use a Start to Start rule, minus 4 weeks (so 4 weeks prior to class, these items need to be complete. Then 3 weeks prior, 2 weeks prior, etc. It automatically calculates the timeline based on the class start date entered at the top. You can even do this for after class. For instance, if you have things to follow up on a week after that date, then would use 17SS +1w.
I created a template, and any time they have a new class, they start with that template, enter the class date, and they are off and running.
Hope this helps!
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 62.7K Get Help
- 371 Global Discussions
- 203 Industry Talk
- 436 Announcements
- 4.5K Ideas & Feature Requests
- 137 Brandfolder
- 129 Just for fun
- 129 Community Job Board
- 448 Show & Tell
- 30 Member Spotlight
- 1 SmartStories
- 282 Events
- 32 Webinars
- 7.3K Forum Archives