Period of validity and reuse of update requests
Hi.
Do you know if there is any way to use and reuse an update request for a period of time?
Regards.
Juan Carlos Reguera
Answers
-
You can't "reuse" an update request, but you can have multiple requests sent out. Can you provide more detail into your process? We may be able to help come up with some kind of solution for you.
-
Hi.
I need the column value in the middle of the week to send a forecast for the weekend. The final value will be the one you have on Friday and can vary from the forecast.
Modification should be requested by users. Forwarding a request to everyone on Friday shouldn't be an option.
Thank you.
Regards.
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 63.5K Get Help
- 402 Global Discussions
- 213 Industry Talk
- 450 Announcements
- 4.7K Ideas & Feature Requests
- 141 Brandfolder
- 135 Just for fun
- 56 Community Job Board
- 454 Show & Tell
- 31 Member Spotlight
- 1 SmartStories
- 296 Events
- 36 Webinars
- 7.3K Forum Archives